It's time to forge ahead-Shenhua people make every effort to advance the project construction in an orderly manner!
- Categories:Shenhua News
- Author:
- Origin:
- Time of issue:2020-04-25 19:17
- Views:
(Summary description)At present, the new crown virus is still spreading around the world. Although the domestic epidemic situation has turned around, the situation is still not optimistic. Under the premise of doing a good job in epidemic prevention and control, our company is making every effort to advance the construction of projects that have been undertaken in an orderly manner. In order to complete the projects that have been undertaken on time, with quality and quantity, Shenhua people's struggle has appeared on the construction sites in various places.
It's time to forge ahead-Shenhua people make every effort to advance the project construction in an orderly manner!
(Summary description)At present, the new crown virus is still spreading around the world. Although the domestic epidemic situation has turned around, the situation is still not optimistic. Under the premise of doing a good job in epidemic prevention and control, our company is making every effort to advance the construction of projects that have been undertaken in an orderly manner. In order to complete the projects that have been undertaken on time, with quality and quantity, Shenhua people's struggle has appeared on the construction sites in various places.
- Categories:Shenhua News
- Author:
- Origin:
- Time of issue:2020-04-25 19:17
- Views:
At present, the new crown virus is still spreading around the world. Although the domestic epidemic situation has turned around, the situation is still not optimistic. Under the premise of doing a good job in epidemic prevention and control, our company is making every effort to advance the construction of projects that have been undertaken in an orderly manner. In order to complete the projects that have been undertaken on time, with quality and quantity, Shenhua people's struggle has appeared on the construction sites in various places.
The sound barrier project of Shanghai Rail Transit Line 9 was the company's bid for the project in February this year. The project is to add a sound barrier to an already running line. The measurement and installation need to be performed after the train is out of service at night. The sudden epidemic disrupted the original According to the construction plan, the project is facing many difficulties such as shortened construction period, night construction, and high-altitude operations. The members of the project department faced the difficulties, followed the people-oriented principle, strictly implemented various epidemic prevention and control measures, and were making every effort to advance the project construction in an orderly manner.
Shanghai Rail Transit Line 15 has a total length of 42 kilometers, all of which are underground. There are 30 underground stations. The fire doors of the side passages in the section are all supplied and installed by our company. It is required to be completed before mid-July. Recently, the Shanghai Rail Transit Line 15 Construction Company led an acceptance team composed of design, construction, supervision, and inspection units to our company to conduct random inspections on the fire doors of the side passages, and the products all meet the relevant technical requirements.
The side channel fire door is an environmentally friendly noise reduction product specially developed and designed by our company for the working conditions of subway tunnels. It has independent intellectual property rights and has the characteristics of Class A fire protection, wind pressure resistance, automatic opening and closing, durability, and simple maintenance. This product is a new environmental protection and noise reduction product developed by the company in recent years. It truly achieves that people do not have what we have, and we have the best. The product has been widely used in various section tunnels of the Shanghai Metro.
In addition to the sound barrier of Shanghai Rail Transit Line 9 and the fire door project of the side passage of Line 15, the company's other projects in Shanghai, Zhejiang, Guangdong and other places have started construction one after another. The people of Shenhua uphold the spirit of the iron army and go to various projects. Organize and meticulous construction, go all out to advance the construction progress, and minimize the impact of the epidemic on the enterprise.